Planning, process & cost
How a kitchen fit actually runs, stage by stage
Knowing the sequence tells you where the waiting happens and why.

A kitchen is not one job, it is several trades in a fixed order, and each one is waiting on the one before. Most of the frustration people experience during a kitchen installation comes from not knowing that order — particularly the gap between carcasses going in and a templated worktop arriving. Understanding the sequence makes it far easier to plan around, and to see where a delay is genuinely avoidable.
1. Survey and setting out
Measurements are checked against the plan, and any out-of-square walls, service positions and floor level changes are identified. Problems found here are cheap; the same problems found on fitting day are not.
2. Strip out and making good
Old units, worktops and appliances out, and the walls and floor assessed. This is when hidden issues appear — old tiling adhesive, uneven plaster, a floor that steps across the room.
3. First fix
Plumbing and electrical positions are set to the new layout. Anything that will be buried in the wall or under the floor has to be right at this point, because it becomes very expensive to change afterwards.
4. Carcasses, levelling and appliances
The base units are built and levelled to a datum line across the whole run — this is the single stage that determines whether the finished kitchen looks straight. Appliance housings are set out at this point too.
5. Worktop template and the wait
Stone and solid-surface tops are templated on the levelled carcasses and then fabricated off site, which introduces a genuine gap in the programme. Laminate tops can usually be cut and fitted on site with no wait. This is the difference people most often do not plan for.
6. Second fix, doors and snagging
Sink and appliance connections, doors and drawers hung and aligned to a line, handles, end panels scribed, kickboards scribed to the floor, and a snagging walk-round. The quality of this stage is what people actually see every day.
Questions we're asked about this
Planning a kitchen installation?
Send your plan or unit list and a couple of photos of the room and we'll talk through the sequence and timing.
Get a free quote
Reply within 24 hours - No obligation